Tested tool guide
Tested browser tools
Checked August 16, 2026
What Earned Value Management Calculator does, with a checked example
Translate a project's status-date baseline and actuals into cost and schedule performance indicators plus an updated completion forecast. Enter budget at completion (BAC), planned value (PV), earned value (EV), and actual cost (AC); the result reports CPI, SPI, EAC, ETC, and VAC, while the S-curve shows cumulative separation over time. The common mistake is treating EV as revenue or spending. EV is the budgeted value of work actually completed at the status date.
Worked example
A concrete input and expected output from the current implementation.
Input
BAC: $100,000
PV: $40,000
EV: $40,000
AC: $40,000
->
Expected output
CPI: 1.00; SPI: 1.00; EAC: $100,000; ETC: $60,000; VAC: $0
Both indices are 40,000 / 40,000 = 1.00. Common index-based forecast formulas therefore coincide at BAC; ETC is 100,000 - 40,000 = 60,000, and VAC is 100,000 - 100,000 = 0.