Tested tool guide
Tested browser tools
Checked August 16, 2026
What Change Order Cost Calculator does, with a checked example
A change that reads as one extra outlet on the drawings becomes a contract figure only when hours, rates, materials, and markup sit on the same sheet. This calculator builds a change order price from labor hours and pay rates, material and equipment costs, and a markup you set, then records the schedule impact - how many working days the change adds - beside the dollar total. The surprise is that markup is not profit: it also has to carry overhead, risk, and the cost of the delay, so a percentage that looks generous on a small change often thins out once overhead is paid.
Worked example
A concrete input and expected output from the current implementation.
Input
Labor: 40 hours at $75/h. Materials: $2,500. Overhead: 10% on direct costs. Markup: 15% on the subtotal. Schedule impact: +2 working days on a project due in 12 weeks.
->
Expected output
Direct costs: $5,500 (labor $3,000 + materials $2,500). Overhead: $550. Subtotal: $6,050. Markup: $907.50. Change order total: $6,957.50. Revised completion: original due date + 2 working days.
40 hours x $75 = $3,000 labor, so direct costs total $5,500; overhead of 10% adds $550 and markup of 15% on the $6,050 subtotal adds $907.50, giving $6,957.50. The completion date shifts by the two entered working days - the calculator prices the change, it does not derive the delay.